At project level
last modified August 28, 2007 by jladage
During the project, new stories will be added and estimates will change.
See attachments
A number of graphs and tables will be added to the project view to provide a better insight in the current status of the project.
charts
- Burndown chart of Story points remaining per iterations
- Actual and Planned velocity per iteration
Progress and changes during all iterations.
| Story points at start of iteration | 130 | 113 | 78 | 31 |
| Story points completed | 45 | 47 | 48 | 31 |
| Changes estimates | 10 | 4 | -3 | |
| Story points from new stories | 18 | 8 | 4 | |
| Story points at end of iteration | 113 | 78 | 31 | 0 |