• At project level

  last modified August 28, 2007 by jladage

During the project, new stories will be added and estimates will change.

See attachments

A number of graphs and tables will be added to the project view to provide a better insight in the current status of the project.


charts

  • Burndown chart of Story points remaining per iterations

  • Actual and Planned velocity per iteration
Table

Progress and changes during all iterations.

1 2 3 4
Story points at start of iteration 130 113 78 31
Story points completed 45 47 48 31
Changes estimates 10 4 -3
Story points from new stories 18 8 4
Story points at end of iteration 113 78 31 0