• TOPP Design discussion

LS Design Work

from Rolando Penate on 2008-05-01 18:19
Hello Design Team,

We certainly have our work cut out for us in the next month! In an  
effort to launch the Livable Streets Network before the conference in  
Portland on June 16th we're going to be pushing for a June 2nd  
release.  The calendar is available here:  http://www.openplans.org/projects/streets/to-do-for-livable-streets-network-release

It's pretty ambitious—allocates 5 days for getting sblog and sfilms up  
and running and 5 days for getting groups all styled—so I want to get  
an idea about how comfortable we are with it, whether we think it is  
reasonably achievable, etc. Chris, what's your estimate as to how long  
it'll take? Should we get Phil involved? Is the training overhead  
required for working in OpenCore worth it? Carly, how are you with  
workload required to support this, anything we can do to help?

I'm CCing the streets-discussion list for archiving purposes.

Best,
Rollie


*TIMELINES*

BL
05/02 F: Stage.livablestreets site updated with new copy
05/05 M: Transition plan for NYCstreets->LSN
05/07 W: Review groups and LSN for tone
05/09 F: First Draft of Help Wiki
05/09 F: Streetswiki homepage
05/14 W: Send email to current NYCstreets users about switch
05/23 F: Final site copy

CP/PA/RP
05/07 W: First draft of streetsblog & streetfilms due
05/09 F: LSN and Groups homepages produced
05/14 W: Styles applied to LSN Groups
05/19 M: Design fully implemented